This strategy sets out how council will manage waste and recycling services across the shire through to 2030 and has been updated following the conclusion of the Waste and Recycling Service Review conducted in October last year. It also highlights council's proposed rollout of the four-stream waste service (i.e. the introduction of glass and FOGO recycling).
Find out more
Several council grant funding streams are now open for applications including the Tourism Events Grant which closes on March 9, and the Community Grant, Arts and Culture Grant and Creative Education Fund which all close on March 31. Further information can be found on our website via the link below.
The project, which started as a priority project of the Northern Grampians Youth Strategy in 2014, followed by suitable site reviews in 2019, design in 2022 and construction in April 2023, has seen a major redevelopment to deliver a modern space at the Stawell skate park that will better serve the community for years to come.
The new skate park caters for both new users with areas for them to learn new skills and experienced users with space for them to perform and refine their skate tricks. It’s a fantastic addition to Stawell’s North Park precinct.
9 June - 23 June 2022.
Review community feedback and endorse any changes to current concept design.
Late June 2022.
End of June 2022.
Open throughout July for all skate park construction companies as part of normal competitive tender process.
5 September 2022.
April 2023 and completed August 2023.
September 2019.
December 2020.
January 2021 - December 2021.
December 2021.
30 March 2022.
April 2022.
17 May 2022.
June 2022.
Working group to meet at least four times between the start of the project and the finish of the project.
The group is to provide input and support responsibilities for organising the opening event in 2023 and ongoing programming ideas for the future use of the facility.