This strategy sets out how council will manage waste and recycling services across the shire through to 2030 and has been updated following the conclusion of the Waste and Recycling Service Review conducted in October last year. It also highlights council's proposed rollout of the four-stream waste service (i.e. the introduction of glass and FOGO recycling).
Find out more
Several council grant funding streams are now open for applications including the Tourism Events Grant which closes on March 9, and the Community Grant, Arts and Culture Grant and Creative Education Fund which all close on March 31. Further information can be found on our website via the link below.
The Market Square Restroom Project is an outcome of the 2018 Market Square Masterplan (Plan).
Market Square has been an integral part of the Civic Precinct and community aspirations to improve not only the appeal of the space, but ensure it remains an ideal location to attract locals and visitors alike.
This project builds upon the existing uses and features of the site while increasing Market Square’s amenity, accessibility and attraction for the community and its visitors. The project responds to community engagement findings and assists with future capacity for the park.
Design engagement was conducted in early December 2024 via a Community Engagement Survey. Voting was open for two weeks with Pale Eucalypt (see below) receiving the highest number of votes and therefore selected as the desired colour scheme for the project.
Market Square is a small park situated in the center of St Arnaud – directly behind the main street and council buildings. The park is already well used by the community with several existing features and attractions. These include a performance space, skate park, playground and a sloping shaded lawn beneath mature trees. Market Square is currently used for large community gatherings and informal play by the kindergarten, local children and their families.
The development of the Market Square Master Plan aimed to create a visible, accessible and flexible community space that supports both large formal and small informal community and visitor gatherings. The master plan has considered the broader context of Market Square within St Arnaud along with a more detailed analysis of the existing site opportunities and constraints. The design has been developed in consultation with the project team, council and the community.
This master plan is intended to:
Key considerations of the masterplan included:
The four stages below have been created to either run in consecutive order, one-by-one or as one set of activities simultaneously. These projects align with council's capital strategy and will be completed in specific stages.
Stage 1: Junior Play & Surrounds - Completed
Stage 2: Nature Play Area - Completed
Stage 3: Car Park and Senior Play Area – To be delivered
Stage 4: Restrooms - In Progress (the restroom project has been brought forward due to the availability of funding specific to this infrastructure)
Northern Grampians Shire Council, assisted by Jeavons Landscape Architects, engaged with the community about their needs and wants for market square using several strategies, including: